Maintenance & Project Plan
Deferred Maintenance:
2013
- Replace Electronic Member Gate: Complete
- Replace Clubhouse Roof: Acquiring Bids
- Sweep Front Bays with Magnets for Steel / Scrap: Complete
- Cut Up and Dispose of Damaged Steel Table: Complete
- Replace Flood Damaged Safe and Bay Table Tops
Projects Plan:
2013- Install Permanent Bay Covers Bays 1-5: Complete
- Install Plate Rack in Bay 2 for Member Use: Complete
- Contractor Bids to Permit & Add Additional Bay(s): Design Definitized
Contingency Repairs:
- Berm Height Restoration & Planting- Add Gravel to Bays and Roads
Long Term Plan Estimate:
- Add Additional Bay(s)
- Cut Right Oblique Gravel Road from Front Gate to Pole Barn
- Pole Barn Circular Drive
- Elec Svc to Bays 1-5
The Proponent of this Plan is the ACC Treasurer